Skip to the plan

DreamFieldsA plan for the Associate Vice President, Manufacturing Operations, Security & Facilities

seven sites.one standard.

Where I’d be every day, what I’d do every hour, how each plant gets followed up between visits, and how seven sites get to one audited scorecard, then to live daily production and cost numbers.

Start with day one
7
plants
5
states
4
week rotation
45%
travel · cap is 50%
Right now in the plan
Tempe
Home base
The rotation, mapped to today
Now
Tier 3 with every plant
9:00 Eastern, fifteen minutes, every plant manager on one screen.
Next
The rotation repeats every four weeks.See the day →
The rotationEvery four weeks

The seven plants come from public job postings and press. Nearby locations, like the Madison Heights warehouse and postings in Banning, CA, ride along with the closest plant’s visit. I’d confirm the full list in week one.

Pre-roll capacity
24,000/shift
eight people, $0.06 direct labor a unit
Hand-trim cost
$90→$35/lb
at Vertis, in six months
Manufacturing revenue
$10.5M/yr
up from $1.2M at Vertis
Nectar Bee
4→75people
$850K to $16.6M in revenue
The 2:30 version

the whole plan, in two and a half minutes.

Every part of this page as a short film. It plays without sound, so it works with the volume off. Tap a chapter to jump to it.

00The short version

six doubts, answered.

If I were hiring for this role, these are the questions I’d want answered. Each one links to the part of the plan that answers it.

01The rotation

four weeks. every floor.

Home base is Tempe. Phoenix Sky Harbor flies nonstop to every plant’s airport, so each trip is one flight out and one flight home. Two weeks a month on the road, two at home running the remote cadence. Press play to watch a full rotation, or pick any day.

Week 2 · WednesdayTempe → Hazel Park
Tier 3 · every plant · every weekday · 9:00 ET
Home base Plant HQ + Midwest loop Northeast loop Drive Video site review Remote data audit Actions or partner review Partner-made states
45%travel
Away 9 of 20 working days · 6 nights every four weeks
Posting: up to 50%
Wk 1 · Home baseWk 2 · HQ + MidwestWk 3 · Home + partnersWk 4 · Northeast

Why Tempe: Phoenix Sky Harbor flies nonstop to Palm Springs, Detroit, Newark and Boston. From Palm Springs, Detroit and Boston take a connection and Newark is seasonal. Flights and drive times are typical, not booked.

Pick a dayDay 8 of 20
Week 1Home base
Week 2HQ + Midwest
Week 3Home + partners
Week 4Northeast
Play the four weeks
or use ← → keys
Week 2 · WednesdayHQ + Midwest
Tempe → Hazel Park
PHX → DTW · 7:45 AM AZBooked

Tempe’s first-shift huddles, Tier 3 from the gate, a nonstop to Detroit, then Hazel Park’s second shift and the Madison Heights warehouse.

Key times · Arizona unless marked
  • 5:00 AMAZTempe line boards
  • 7:00 AMTier 3 from the PHX gate
  • 7:45 AMFly PHX → DTW
  • 2:30 PMETHazel Park second shift
  • 4:00 PMMadison Heights warehouse: security walk
Follow-ups that day
  • Actions due in the tracker: Desert Hot Springs
  • Desert Hot Springs actions in the tracker: owners and dates within 48 hours
02Hour by hour

the days, by the hour.

Four kinds of day, including the first one. Times are local to where I am. Hover or tap any block to see what it’s for.

Desert Hot Springs
My first Monday · Pacific time

Day one is for seeing the floor before anyone briefs me on it, meeting the people who run the plants, security, maintenance and money, and leaving with every plant’s first visit booked.

11 h
4:45 AM to 3:45 PM
4 AM6 AM8 AM10 AM12 PM2 PM4 PM
Floor 2 h 45Data 45 minPeople 3 hSecurity & facilities 2 h 30Enterprise 2 h
4:45 AM
Walk in with first shift

The plant manager meets me at the door, and I’m escorted and logged until my badge is issued. Watch start-up: attendance, line clearance, materials staged.

15 min
5:00 AM
Tier 1 huddles

Watch two line boards. Day one is for listening, not running.

30 min
5:30 AM
The site huddle

Watch how the site runs its daily meeting today: who owns which number, and what happens when one goes red.

30 min
6:00 AM
Follow one product

Walk one pre-roll SKU from material issue to finished goods with the plant manager. Count stations and people; time ten cycles at the slowest station.

1 h 30
7:30 AM
First-shift supervisors

Coffee and one question: what gets in your way most days?

30 min
8:00 AM
The COO

The site list, priorities, decision rights, and what good looks like at day 90. Book the weekly Tier 4.

1 h
9:00 AM
Regional directors, then every plant manager

Thirty minutes with the regional directors, then ten with each plant manager while it’s still their working day: their biggest problem, and the best day to walk in with their first shift. First visits booked.

1 h 30
10:30 AM
Security walk

With the security lead: perimeter, doors, the camera map against real coverage, vault, transport staging, officer post orders and licenses, the last twelve months of incidents.

1 h 30
12:00 PM
Lunch in the break room

Sit with the crew. Listen more than I talk.

30 min
12:30 PM
Maintenance and facilities

With the maintenance lead: the PM backlog, the top causes of downtime, critical spares, open capex and construction.

1 h
1:30 PM
Second-shift start

See the handoff between shifts.

30 min
2:00 PM
Finance

How cost per unit is built today and what’s reported weekly. Agree on one cost bridge from the floor to the P&L.

1 h
3:00 PM
Badge, laptop and data access

Request read access to line data, timeclock and labor-cost exports, METRC, the maintenance system and security logs.

15 min
3:15 PM
Day-one note

One page to the COO: what I saw, what I asked for, what happens the rest of the week.

30 min
Tyngsboro + Lowell
Week 4 · Thursday · Eastern time

A visit day starts when the crew does. Everything I check, I check where the work happens. This one ends on Lowell’s second shift, fifteen minutes away.

11 h
4:45 AM to 3:45 PM
4 AM6 AM8 AM10 AM12 PM2 PM4 PM
Floor 2 h 30Data 3 h 15People 3 h 30Security & facilities 1 hEnterprise 30 minTravel 15 min
4:45 AM
Walk in with first shift

Same door and badge check as the crew. The first look at access control is the one every employee gets.

15 min
5:00 AM
Tier 1 huddles on two lines

Ten minutes each at the line board: yesterday’s count, today’s plan, one problem.

30 min
5:30 AM
Floor walk with the plant manager

Time ten cycles at three manual stations. Check line clearance and label verification on the automated lines.

1 h
6:30 AM
Tier 2 site huddle

Supervisors, maintenance, QA and security with the plant manager. Every red leaves with an owner.

30 min
7:00 AM
Data audit on site

Yesterday’s shift log for two lines and three random batch records, traced to METRC and the timeclock.

1 h
8:00 AM
Security and facilities walk

Camera coverage against the site map, access exceptions, officer licenses, vault and transport steps, the maintenance backlog.

1 h
9:00 AM
Tier 3 with every plant

Fifteen minutes on one screen, run from this site’s board. Plant managers see each other’s reds and offer help.

30 min
9:30 AM
Plant manager one-on-one

Scorecard, open countermeasures, people and capex asks. Ends with dated actions.

1 h
10:30 AM
Supervisor academy module

Taught on the floor in 45 minutes, with Lowell’s supervisors in the room. This visit: find the bottleneck by timing a line.

1 h
11:30 AM
Lunch in the break room

Listen. Morale shows up on the floor long before it shows up on a scorecard.

30 min
12:00 PM
Work the top loss

The A3 on this site’s biggest loss, reviewed with its owner on the floor. Is the fix working?

1 h
1:00 PM
Visit summary out

AI drafts it from my notes and the day’s data. I edit it and send it to the plant manager before I leave the building.

15 min
1:15 PM
Drive to Lowell

Fifteen minutes.

15 min
1:30 PM
Lowell second-shift start

Tier 1 with Lowell’s second shift, then the first hour on their floor. Both shifts run the same standard.

45 min
2:15 PM
Coffee with a supervisor

A different supervisor each visit, this time from Lowell’s second shift. One coaching topic, and one question: what’s in your way?

30 min
2:45 PM
The day’s notes

AI drafts them from my notes and the day’s data. I edit them and send them before I leave. Lowell’s first shift is tomorrow.

1 h
Tempe
Week 1 · Tuesday · Arizona time

Home weeks run the remote cadence: every site reviewed by video, one site audited every day, and time on the Tempe floor. Times are for winter; Arizona skips daylight saving, so from March to November anything set in Eastern time lands an hour earlier.

11 h
4:30 AM to 3:30 PM
4 AM6 AM8 AM10 AM12 PM2 PM4 PM
Floor 1 h 30Data 2 hPeople 4 hSecurity & facilities 1 h 30Enterprise 2 h
4:30 AM
The morning numbers

What moved overnight, what’s red, and who owns it. By month twelve, the AI brief writes this.

30 min
5:00 AM
First-shift line boards

The home site runs the same standard. Walk two line boards at Tier 1.

30 min
5:30 AM
Tier 2, Tempe

The plant manager runs it. I listen.

30 min
6:00 AM
Floor walk

A different area each day: production, processing, warehouse, maintenance.

1 h
7:00 AM
Tier 3 with every plant

9:00 Eastern, fifteen minutes, every plant manager on one screen.

30 min
7:30 AM
Remote data audit

One site a day: five random records traced from shift log to METRC to timeclock to scorecard.

1 h
8:30 AM
Approvals and hiring

Capex, hiring and purchase approvals, so nothing waits on me.

30 min
9:00 AM
Video site reviews

Two sites a day, 45 minutes each, with the plant manager and their regional director. Every site gets a review or a visit every week.

1 h 30
10:30 AM
Tier 4 with the COO and Finance

Tuesdays, by video. The week in dollars: what the gains are worth and what the misses cost. Once a month it’s the business review, in person at headquarters.

1 h
11:30 AM
Lunch on the floor

Same rule as on the road.

1 h
12:30 PM
Security and facilities program

Standards, investigations with HR and Legal, officer licensing, continuity drills, contractor and capex reviews.

1 h 30
2:00 PM
Direct-report one-on-ones

Regional directors, security and facilities leads. Same slot every week; by video when I’m on the road.

1 h
3:00 PM
Close the loop

Action tracker review. Anything past its date gets a call today.

30 min
Tempe → Hazel Park
Week 2 · Wednesday · Arizona time

Every flight is a nonstop out of Phoenix. Travel days start at home and end on a plant floor, or start on a floor and end at home.

11 h
4:30 AM to 3:30 PM
4 AM6 AM8 AM10 AM12 PM2 PM4 PM
Floor 2 hData 1 hPeople 30 minSecurity & facilities 1 hEnterprise 45 minTravel 5 h 45
4:30 AM
The morning numbers

At home. What moved overnight, what’s red, and who owns it.

30 min
5:00 AM
Tempe line boards

Tier 1 on two lines at the home plant.

30 min
5:30 AM
Tier 2, Tempe

The plant manager runs it. I listen, then head to the airport.

30 min
6:00 AM
To PHX

Ten minutes from the plant. Security, then Hazel Park’s packet at the gate.

1 h
7:00 AM
Tier 3 from the gate

9:00 Eastern, fifteen minutes, every plant manager on one screen. Then board.

45 min
7:45 AM
Fly PHX → DTW

About four hours, nonstop. On the plane: Hazel Park’s last four scorecards, open actions from the last visit, this week’s audit picks.

3 h 55
11:40 AM
Land in Detroit, drive to Hazel Park

1:40 PM Eastern. About thirty minutes to the plant.

50 min
12:30 PM
Hazel Park second shift

2:30 PM Eastern. Walk second shift with its supervisors: the board, the handoff from first shift, the slowest station.

1 h 30
2:00 PM
Madison Heights warehouse

4:00 PM Eastern. Security walk: cameras, access, the vault and transport staging.

1 h
3:00 PM
Notes for tomorrow

5:00 PM Eastern. First shift starts at 5:00, and tomorrow is the full visit day.

30 min

Tier 3 runs at 9:00 Eastern every weekday: 7:00 in Arizona in winter, 6:00 in summer, and 6:00 Pacific. Where I don’t know a site’s shift times yet, I’ve assumed first shift at 5:00 AM and second at about 1:30 PM. I’d confirm each site’s in week one.

03Between visits

no plant goes a day without contact.

A visit is two days in twenty-eight. The other twenty-six are where the follow-up happens. Here’s one plant’s month, using Hazel Park.

2
days on the floor
1
written summary
20
Tier 3 calls
3
video site reviews
5
data audits
Visit · WedDay 7Day 14Day 21Day 28
In person
Two days on the floor. The next visit verifies the fixes.
On site
Next visit
Written summary
Sent the day the visit ends: what I saw, what we agreed, with the numbers.
Actions, owned and dated
In the shared tracker within 48 hours. Example: nine actions closing over three weeks.
9 open0 open
Tier 3 call
15 minutes every weekday at 9:00 ET. Overdue actions show by name.
Video site review
Weekly, with the plant manager and regional director, in the weeks I’m not on site.
Data audit
Five records traced to source every week. I spot-check from home.
My spot check

Weekends shaded. The action burn-down is an example of how the tracker reads, not real data.

04One standard

one scorecard. one cadence.

Every site reports the same numbers, in the same order, owned by name, and every number ladders up to contribution margin per unit. Click any number for its formula, source, owner and rule.

Cost

Throughput

Quality

Safety, security & facilities

People

Targets come from each site’s own 30-day baseline. No number on this page is a DreamFields target.

The number everything feeds
Contribution margin per unit

What each unit leaves after the costs that move with volume.

Net price − variable cost per unit
Source
Finance
Owner
COO and Finance. I own the cost side.
Cadence
Weekly estimate, monthly close
The ruleEvery branch below feeds this number. An improvement that never reaches it didn’t happen.

the huddle cadence.

Four tiers, fifteen minutes or less, the same at every plant. Problems climb until someone can fix them, and fixes travel to every site with the same machine.

Tier 1
10 min
Line lead and crew
Start of every shift

Yesterday’s count, today’s plan, one problem. At the line board.

Tier 2
15 min
Supervisors, maintenance, QA and security with the plant manager
5:30 West · 6:30 East

The site board. Every red leaves with an owner.

Tier 3
15 min
Every plant manager, the regional directors and me
9:00 ET every weekday

One screen. Reds over two days, overdue actions, help needed between sites.

Tier 4
45 min
Me, the COO and Finance
Tuesdays by video · monthly in person at HQ

The week in dollars: what the gains are worth and what the misses cost.

Example: one problem, climbing the tiers
5:42 AM
A labeler jams after a changeover

The operator calls maintenance and logs a reason code on the line tablet.

5:50 AM
Maintenance at the line

Running again by 6:10. The cause is logged; the fix is temporary.

6:30 AM
Tier 2

The maintenance lead owns the permanent fix.

9:00 AM
Tier 3 with every plant

Another site runs the same labeler and shares its setting.

Thursday
Fixed and copied

Verified on the floor. The setting goes into standard work at every site with that machine.

05Supervisor academy

supervisors run the floor.

Nine modules, each taught on the floor in 45 minutes and finished with an assignment on the supervisor’s own line. It covers what the posting asks for: root cause, Lean, cycle time, bottlenecks and corrective action.

1
Read your line

OEE and units per labor-hour from your own board.

Explain yesterday’s numbers at Tier 1 without notes.

2
Time a station

Cycle time, takt time, and the ten-cycle study.

Time ten cycles at two stations and post the result.

3
Find the bottleneck

Where the line actually waits, and why adding people anywhere else does nothing.

Find your line’s constraint and prove it with timings.

4
Standard work

Write it, train it, check it.

Write standard work for one station and train two operators on it.

5
Root cause

Five whys and fishbone on a real stop.

Run a root cause on a stop from this week.

6
Fix it for good

A3s and corrective actions that stay fixed.

Close one corrective action and show it held for two weeks.

7
Run the huddle

Tier 1 in ten minutes, Tier 2 in fifteen.

Run Tier 1 every day for a week, observed twice.

8
Lead the crew

Feedback, recognition, attendance, and the labor agreements, New York’s included. Taught with HR.

One recognition and one coaching conversation, logged.

New
9
Decide with AI and data

Use AI tools to analyze your line’s data, see what changed and why, and make a better call. Then check it on the floor.

Analyze a week of your line’s data with an AI tool and bring one decision to Tier 2.

A module counts when the supervisor has run it on their own line and the plant manager has seen it.
Days 29–56
Cohort one

The two pilot sites. I teach it.

By month six
Every site

Every supervisor through modules one to seven.

Month six on
Plant managers teach

Which is how it scales past me. Successors named for every plant manager.

06Workbench

try the math.

Two tools I’d use with every plant manager in the first month. The first starts from my own pre-roll line. Change anything.

A line only runs as fast as its slowest station. Add or move people, change cycle times, and watch where the units pile up.

The line, running at 12× speed · each dot is a pre-roll

Eight people, 24,000 per 8-hour shift, $0.06 direct labor per unit. The station breakdown is illustrative.

The posting asks for OEE gains translated into financial results. Here’s the arithmetic, both ways: more units if demand takes them, fewer line-hours if it doesn’t.

Placeholder numbers · put in yours

OEE today

85%
80%
88%
A × P × Q = 60%
+5

The lines

12
60
80
$0.40

If demand doesn’t take the units

6
$22.50
What +5 points of OEE is worth, if demand takes the units
$0a year
One point of OEE
$0

If demand doesn’t take the units
0 line-hours

100M
Every cent off cost per unit: $1.0M a year
07Data audits and accountability

trust the numbers first.

A scorecard is only as good as its worst number. Every week, random records get traced back to source, and a number that fails doesn’t count until it’s fixed.

One record, traced end to end
Shift log

Line 2 · second shift

6,240 units
METRC package

Pre-roll package

6,240 units
Timeclock

8 people on the line

64.0 hours
Scorecard

Units per labor-hour

97.5
Press a button to trace a record.

the audit cadence.

Automatic checks every day, a human trace every week, a trust score every month, and on-site audits every quarter.

Daily
Automatic

Every line and station reports within 30 minutes of shift end. Out-of-range numbers are flagged, never deleted. Reported units are checked against METRC packages.

Weekly
Site data leads, plus my spot checks

Five random records per site, traced end to end: shift log → METRC package → timeclock hours → scorecard. All four have to agree.

Monthly
Data trust score

The share of audited records that matched source. It sits next to every site’s scorecard, and a site’s numbers count once its trust is high.

Quarterly
Partners and security

On-site audits of each manufacturing partner, and a security audit at every owned site: camera map, access logs, officer licenses, transport steps.

accountability, in writing.

The same rules at every site, for every number.

  1. 01Every number has one owner, by name.
  2. 02Same scorecard, same order, at every site. Posted on the floor.
  3. 03Red two days running: the owner brings a countermeasure to Tier 2.
  4. 04Red five days: an A3 at Tier 4 with the COO.
  5. 05A follow-up past its date stays on the Tier 3 board until it closes.
  6. 06A number that fails an audit doesn’t count until it’s fixed.
  7. 07Recognition follows the measured numbers. Same rules for everyone.
The red clock
Day 1
Shows red on the board
Day 2
Owner brings a countermeasure to Tier 2
Day 3
Countermeasure running
Day 4
Still red? Help from another site
Day 5
A3 at Tier 4 with the COO

A red number never sits. It either gets a countermeasure, gets help, or gets the COO’s attention.

08Security & facilities

protect people, product and facilities.

Two-thirds of this job’s title, and the part my resume says least about. Here’s the program, one standard across five state rulebooks, the audit I’d run at every site in the first 30 days, and what happens on a bad day.

Officers and leads

In-house officers under regional security managers, plus outside providers where we use them. Every license tracked with its expiry date. Written post orders for every post, including use-of-force and weapons rules by state.

Access and surveillance

Badge tiers by role, reviewed quarterly. Visitors logged and escorted. Cameras mapped to every door, vault and limited-access room, with uptime as a daily number. Alarms and intrusion detection tested on a schedule. Video only, no audio.

Inventory and transport

Counts checked against METRC every day. Vault access by two people, logged. Cash under the same controls, and printed packaging counted like product. Transfers on manifests with chain of custody from dock to truck. Waste destroyed and documented to each state’s rule.

Facilities and maintenance

One maintenance system at every site, response times for line-down calls, critical spares on the shelf, fire and life safety inspections on one calendar, contractors scored and insured.

Continuity and response

A playbook for each bad day, an owner for each, drills on a calendar, and one call tree for the company.

One standardfive rulebooks.
DCCCaliforniaADHSArizonaCRAMichiganCCCMassachusettsOCMNew York

Where state rules differ, the standard follows the strictest one, with a one-page appendix per state. Camera audio stays off everywhere, which keeps audio-consent laws out of it; Legal approves camera placement, signage and retention, and there are no cameras in restrooms or locker rooms. Partner sites in Missouri, Ohio, Illinois and Ontario are audited against the same standard as each partner agreement allows, and any medical-licensed site gets a Schedule III readiness review with Compliance and Legal.

the first-30-days audit.

The same checklist at every owned site. Tick through it.

0 of 24 checks
Cameras3
Access3
Vault3
Inventory3
Transport3
Officers3
Alarms3
Continuity3
All 24 checks done: that’s one site’s day-30 page, ready for the COO.

pick a bad day.

Every scenario has a playbook, an owner and a drill on the calendar. Here’s the first 15 minutes, the first hour and the first day.

Scenario
Break-in or robbery attempt
First 15 minutes

People first: comply, nobody resists. Panic alarm only if it’s safe. Call 911 once they’ve left, then lock down and account for everyone. The security lead calls me.

First hour

Preserve all video. Start the incident log. Compliance starts the regulator and police notices. Once police release the scene, two people count the vault against METRC.

First day

Regulator notice confirmed within the state’s deadline. Insurance claim. The point of entry fixed before the next shift.

OwnerRegional security manager
DrillTwice a year at every site
Escalates toMe, then the COO

facilities standards.

Maintenance, construction and capital, run the same way at every site.

  • Line-down calls: a technician at the line within a response time set from the baseline, every shift.
  • Preventive maintenance done on time, tracked in one maintenance system.
  • Critical spares for every bottleneck machine, counted monthly.
  • Contractors: no current insurance certificate, no badge. Every contractor scored on safety, schedule, budget and quality.
  • Capex: every ask on one sheet, ranked by payback, effect on OEE, and risk.
  • Fire and life safety inspections for every site on one calendar.
09Day one to day 90

day one is already planned.

The first week day by day, the first 90 days in three cycles that match three laps of the rotation, and the year that follows. Drag through the year to see where everything stands.

Day 1 · Mon
See it first

First shift at 5:00, then the COO, security, maintenance, Finance and every plant manager.

Day 2 · Tue
The data

A second first shift, in processing and packaging. QA and Compliance leads, and my state agent registrations started so I can walk every floor. HR: org charts, open roles, 90-day turnover. Pull 90 days of what each site reports today.

Day 3 · Wed
The first Tier 3

Every plant manager on one call: three questions, fifteen minutes. Home to Tempe: first shift on my home floor, and a video site review with Hazel Park. Start the officer license list: every officer, every license, every expiry date.

Day 4 · Thu
The baseline

Video site reviews with Middletown, Peekskill, Tyngsboro and Lowell. Downtime by cause from the maintenance system. The one-page baseline template, the same for every site.

Day 5 · Fri
Partners and the plan

Meet whoever owns the partner relationships, then the Missouri, Ohio, Illinois and Ontario partners. A week-one note to the COO. Week two booked: Desert Hot Springs and Hazel Park.

three laps, three cycles.

Each 28-day cycle is one lap of the rotation, and ends with something you can hold me to.

Days 1–28
Listen and baseline
  • First shift at every owned site. Time the stations, read the boards, meet every supervisor.
  • Baseline OEE on every automated line and units per labor-hour at every manual station.
  • Security audit at every site: camera map, access tiers, officer licensing, alarms, the incident log.
  • Maintenance backlog, downtime by cause, and open construction, site by site.
Day 30: one page per site with its baseline, its three biggest losses, and its security gaps ranked.
Days 29–56
One standard
  • One scorecard and one KPI tree, in the same order at every site.
  • Tier 1, 2 and 3 huddles running at all seven sites.
  • Weekly data audits start. Every number gets one owner, by name.
  • Supervisor academy, cohort one, at the two pilot sites.
Day 56: two pilot lines running the new standard, one automated and one manual.
Days 57–90
Prove it, then copy it
  • Pilot results, before and after, in units and dollars.
  • Pilot standard work copied to every site with the same equipment.
  • Security standard version one and the continuity playbook, drilled at two sites.
  • A capex plan ranked by return: throughput, cost, and risk.
Day 90: the first quarterly business review with Finance: gains in dollars and next quarter’s targets.

the first year.

Months four to twelve make the standard live: machines first, then manual stations, then daily cost, then the AI layer.

Day 1Monday
Day one

First shift at 5:00.

Day 1Day 30Day 60Day 90Month 6Month 9Month 12
The plan
Listen and baseline
One standard
Prove it, copy it
Make it live
Data
Typed in, audited weekly
Machine OEE
Tablets + timeclock
Daily cost
AI layer
Security & facilities
Audit every site
Standard v1 + playbook
Quarterly audits and drills
Supervisors
Cohort one
Every site
Plant managers teach
Milestones

every working day of year one.

Thirteen laps of the same rotation. The pattern doesn’t change, so every plant can plan around it.

13visits to every plant
117days on the road
78nights away
260Tier 3 calls
13monthly business reviews
Home baseHQ + MidwestNortheastBusiness reviewPartner dayMilestone
Wk 1 · Home base
Wk 2 · HQ + Midwest
Wk 3 · Home + partners
Wk 4 · Northeast
Lap 1
Lap 2
Lap 3
Lap 4
Lap 5
Lap 6
Lap 7
Lap 8
Lap 9
Lap 10
Lap 11
Lap 12
Lap 13

Every working day of year one, before holidays and PTO. Tap a day to open it in the rotation.

10The end state

live, lean, AI-assisted.

By month twelve, every number arrives on its own, every number traces to source, and an AI layer reads it all first thing every morning. People still decide and own every number.

1Sources
  • Line PLCs and packaging machines
  • Tablets at manual stations
  • Timeclock and payroll
  • METRC
  • ERP costs
  • Lab results
  • Maintenance system
  • Access and camera logs
2One data model
Every unit, minute, gram and dollar, tagged to site, line, shift and SKU.
3AI layer
  • Daily brief
  • Anomaly flags
  • Shift forecasts
  • Drafted countermeasures
  • Questions in plain English
4People
  • Tier 1–4 huddles
  • Plant managers
  • COO and Finance
Nobody types a number twiceOne page per siteFifteen-minute huddlesEvery number traceable to sourceAI drafts, people decide

AI drafts and flags. People decide and own the number.

the control tower.

What the COO, Finance and every plant manager would open each morning. This demo runs a sample morning at 60× speed.

Control tower Demo Thu 9:00 AM ET60× speed Sample data
Units today, all plants, against planActual Plan
PlantUnits todayOEEUnits / labor-hrScheduleData trust28-day OEEStatus
Desert Hot SpringsDHS · 6 lines074%35297%99%On track
TempeTMP · 4 lines071%33895%98%On track
Hazel ParkHZP · 4 lines066%34192%97%Watch
MiddletownMID · 3 lines058%29686%96%Act
PeekskillPKS · 2 lines067%32292%95%On track
TyngsboroTYN · 3 lines069%32994%98%On track
LowellLOW · 2 lines065%31893%91%Watch
Flags and actions0 today
    AI daily brief · 5:00 AMSample brief
      Ask the plant dataDemo
      Answers come from the sample data on this page.
      Sample numbers on your plant names, to show the format. Not DreamFields figures.Status: on track · watch · act
      11Proof

      the receipts.

      Thirteen years building regulated cannabis manufacturing in Colorado, California and Arizona. On the executive team at Vertis today, running 80–100 people through managers and supervisors.

      24,000
      per shift
      Pre-roll capacity at $0.06 a unit

      Capacity for 24,000 per 8-hour shift from an eight-person team, at $0.06 direct labor per unit. $0.07–$0.09 Dutch-crowned and QC’d.

      $90 → $35
      per lb
      Hand-trim cost in six months

      Moved the core team in-house from contract pay onto a performance-based pay band. Ten trimmers walked out; I won them back and promoted their leader. Still our top crew.

      $1.2M → $10.5M
      a year
      Bulk flower into packaged brands

      Grew Vertis manufacturing revenue, mostly by turning bulk flower into packaged products for Bright Lights, 3 Bros and Stereo.

      4 → 75
      people
      A plant from a diner kitchen

      Grew Nectar Bee from a 2,500 sq ft converted kitchen to a purpose-built 22,000 sq ft infused products plant. Revenue from $850K to $16.6M.

      $30K
      a year, every year
      An eQMS I built, with live financials

      I built Vertis’s eQMS platform, including automated live financial reporting. It saves the company about $30K a year. I’m on the executive team and report to the President and the Board.

      EU GMP
      + GACP
      Implemented facility-wide

      Developed and implemented the program across the whole Vertis facility, cultivation included. Six Sigma Black Belt with GMP auditor certification.

      how this page was built.

      About four hours of my time, research included. AI tools did the drafting, coding and charting; I set the direction, and I own every number on it.

      Bigger builds take real work. The eQMS I built at Vertis was a sustained build, and it saves the company about $30K a year, year after year.

      It’s also what I’d teach: empowering supervisors and plant managers to use AI tools to analyze their own data and make better decisions, with a person checking the result on the floor.

      12Talk to me

      let’s
      talk.

      I’d like to walk you through this plan on a call, or on the floor at any of your plants.

      Paso Robles, CA · open to relocation
      Week one

      the first asks.

      • 01The confirmed site list, headcounts and shift times.
      • 02Read access to line data, timeclock and labor-cost exports, METRC, the maintenance system and security logs.
      • 03An hour with each plant manager and each security lead in the first two weeks.
      • 04The last 90 days of whatever each site reports today, so the baseline starts from your numbers.
      Talk to me